Monday, February 20, 2006

Challenges facing the US wind industry

The presentations and gossip at the American Wind Energy Association conference in Denver in May l2005 eft some fans of the US wind energy industry with an impression similar to the opening lines of Charles DickensÕ A Tale Of Two Cities. ÒIt was the best of times, it was the worst of times, it was the age of wisdom, it was the age of foolishness ... Ó

In Denver, optimism was readily apparent from the record pace at which the industry is installing (an anticipated) 2500 MW of turbines in 2005. Installed US capacity at the end of 2004 was 6740 MW. Another sign of enthusiasm was the record number of participants, 4100, (up 14%) that flocked to the annual conference. Many of the newcomers, groomed in suits, represented the growing institutionalisation of what was once a cottage industry.

Reflecting the worst of times, however, was the continuing uncertainty over the fate of the production tax credit (PTC). Under US law current at the time of the conference a tax credit of 1.9 cents/kWh was allowed for the production of electricity from qualified wind energy facilities and other forms of renewable energy. The credit, created by the Energy Policy Act of 1992 is applicable to qualifying wind facilities placed in service before 1 January 2006, The Bush administration budget request called for a two-year PTC extension, while the wind industry was looking for five years. In June, the Senate proposed a 10% federal renewable portfolio standard and a three-year PTC extension. The House proposal in April did not include either provision.

Wind advocates said that removing the production tax credits would not necessarily undermine the industry, but continuing them would be a stabilising factor that would remove the ongoing uncertainty that has created a tentative, boom/bust mentality.

According to AWEA, four to six months before the tax credits expire, financial lenders hesitate to provide capital for wind projects. A rush to complete projects before the deadline creates a herd effect. Developers and sponsors dash to stick pylons in the ground, spiking turbine prices, and they largely recede once the PTCs expire. The US wind industry scored banner years in 2001 (1697 MW), 2003 (1687 MW) but nearly withered in 2000 (67 MW), 2002 (446 MW) and 2004 (389 MW) as a result of production tax uncertainty. By comparison in Germany a simple fixed price incentive has led to a burgeoning market with an installed capacity of 16,629MW at the end of last year. There, producers of renewable energy receive r70 per MWh when sold to a utility and some regions generate as much as 25% of their electricity from wind power.

Bold state initiatives

While questions regarding the federal PTCs have contributed to uncertainty in the market, the strongest drivers of new installations have been initiatives taken at the state level to mandate a minimum amount of electricity to be supplied from renewable sources. At the beginning of 2005, such renewable portfolio standards (RPS) existed in 18 states including the most populated Ð California, Texas and New York. Earlier this year, Illinois proposed legislation that would require 8% of the stateÕs power to come from renewable energy by 2012. In addition to its statewide mandate, the government of Connecticut is planning to purchase 20% of its electricity from renewable sources by 2010 and all of its electricity from renewable by 2050.

California and Texas with 2096 MW and 1293 MW had the greatest installed capacity at the end of 2004 followed by Iowa (632 MW), Minnesota (615 MW) and Wyoming (285 MW). For 2005, major installations are being undertaken in Texas, California, Iowa, Kansas and Oklahoma.

Rising turbine prices

Rising prices for wind turbine generators has complicated the US market. Its on-again, off-again nature, unfavourable dollar/euro exchange rates, and climbing steel and energy prices have all contributed. Mark Little, vice president of Power Generation, GE Energy, said in Denver that the company is supplying 1100 1.5 MW machines into the North American market. ÒWhile we have a strong US supply base, because of the ups and downs of the industry, we have not been able to requisition all of the supplies to fulfil our North American demand. We are looking for some stability ... with stability we could have supplied all of the demand from our US operating base.Ó

Thomas Carbone, president of Vestas Americas, a large supplier to the US market, says that less than 50% of the value creation is from US companies. The intermittency of the PTC adds additional costs to his operation, and precludes Vestas from making the type of investments it needs to make to become a steady and price-stable supplier. ÒThe short planning horizon that has emerged as a result has driven up costs 20% higher,Ó he says. ÒIf we could add more regulatory certainty, we could do a whole lot better than we do now working with one to two-year renewals.Ó

Rising prices have complicated developersÕ efforts to respond to RFPs where they must commit to a price in the form of a bid in a power purchase agreement. Rising turbine prices, as well as balance of plant costs, can undermine a project because it is difficult to legitimately forecast costs a year down the line. This has led to a number of bids for projects that can never be built, or to a lot of renegotiating of rates to which utilities are sometimes sympathetic, sometimes not.

Despite the constraint due to the price of turbines, the economic attractiveness of US wind projects nevertheless remains good, says Vivek Mittal, Bank of Scotland, who is exploring opportunities to finance projects in the US. ÒThere is a good track record of performance so we are interested in diversifying away from Europe ... if somebody is financing wind, the US is important because of the volume of deals and the regulatory framework. The available incentive framework is still good despite the production tax credit uncertainty. Because power prices are high, you can argue that you really donÕt need some incentives. You could do away with the production tax credit in some markets.Ó

Transmission bottlenecks

Capital does not flow readily to transmission projects, and, especially in the wind resource rich northern plain states, incremental transmission investment is necessary for wind to have a big impact. Some analysts contend that it is difficult to envisage that the necessary transmission infrastructure will be in place to support wind energyÕs growth. ÒThere is a great vast resource in the middle of the country, the industry is working with policy makers and the market, but you donÕt want to be the first one in that market and have to pay for that transmission line,Ó says one turbine vendor.

An exception to the rule is the Western Governors Association, which launched an initiative in late 2004 to develop 30 000 MW of clean energy by 2015 and achieve a 20% improvement in energy efficiency by 2020, and is starting a 15-year planning process for expanding transmission

A vision for wind

According to Robert Thresher, director of the National Wind Technology Centre at the National Renewable Energy Laboratory, the US department of EnergyÕs research and development support is aimed at expanding wind energy markets. NREL initiatives support low wind speed technology, off-shore wind, distributed wind technology, and generator drivetrain and power electronics.

At Denver, Thresher characterised the US market in 2005 as consisting of principally land-based, bulk electricity producers capable of generating power at 4 to 6 cents/kWh at wind speeds of 15 mph. By 2012, DOE would like to see on-shore 2 to 5 MW low wind speed turbines (LWST) generate power for 3 cents/kWh at wind speeds of 13 mph. Off-shore by 2012 and beyond, DOE envisions 5 MW and larger machines generating power for 5cents/kWh. Reaching these goals would bring wind sites five times closer to load centres, increase the areas for wind development by a factor of 20, and open significant off-shore wind resources for development.

Toward this end, DOE has awarded, or is negotiating, technology subcontracts to Clipper WindPower Technology for 2.5 MW, 93m rotor distributed drive generators; to Northern Power Systems for 2+ MW direct drive turbines; and to GE Wind Energy for next generation compact integrated drive trains and optimal off-shore full system prototypes.

ÒThe US is blessed with a great wind resource. The wind potential here is greater than the electricity demand,Ó says Thresher. ÒOn-shore development is happening now. The new horizon is moving off-shore and building wind turbines in dry docks for transport to off-shore sites. We can create a whole new energy industry similar to the off-shore oil industry but that is not extractive and that keeps the jobs and benefits at home.Ó

How competitive is wind?

Rising natural gas prices have certainly helped make wind energy more competitive and have provided room for wind to operate in a portfolio of generating options. However, large LNG terminal projects coming on line could depress the price of natural gas, or new large coal-fired plants coming on line, could change the dynamics of the industry and affect the competitiveness of the wind industry, cautions GEÕs Mark Little.

ÒGE Energy will improve the technology, we will drive the cost down but it is hard to say which of the technologies will be most competitive over a period of time.Ó

Technology challenges

To make its turbines more cost competitive, GE is designing bigger, lighter and more sophisticated wind machines. ÒThe whole thrust of modern turbine design is to design a big rotor for high capacity to capture wind energy, yet to design it to mitigate loads more effectively,Ó says Jim Lyons, a chief engineer for GEÕs Electric Systems Technologies. ÒThe industry is scaling up to larger and larger machines. In moving to five to seven MW machines, the entire design paradigm has to shift. Wind turbines are deceptively complex machines.Ó

There are a lot of challenges, Lyons says, in reducing the structural weight of turbines and in creating more intelligent machines that are more compliant, lightweight structures. There is also the challenge of designing and manufacturing bigger blades that are very large composite structures.

Buying components from different vendors and stitching together solutions Ð the way the industry has grown up Ð is simply not going to work anymore as machines get larger, says Lyons. Scaling up results in bigger and heavier machines, so the industry is moving toward compact drive trains where the functions of the main shaft, bearings, gearboxes and generators are combined into more compact assemblies. ÒDoing so can save a tremendous amount of weight,Ó says Lyons. ÒYou can shrink the nacelle and supporting structure from the 400 to 500 ton range to 200 tons. The whole structural design paradigm needs to change to make the economics going forward work.Ó

The same approach applies to blades, where there are some critical internal load bearing structures whose design can take advantage of the extra stiffness of carbon fibre with a minimal amount of material. It is more expensive, but judiciously placed carbon fibre can carry stress loads more effectively and achieve significant weight reduction, enabling much larger blades. ÒThe 6 MW machine would require a blade that is 70 m long,Ó says Lyons. ÒThe biggest rotor constructed to date is 126 metre diameter. The industry consensus to date is that to build off-shore, more power is needed to make the economics work because of the extra costs associated with the electrical distribution networks, cable and foundations systems off-shore.Ó

The UK government, according to Lyons, is pushing the industry to bigger sizes. They plan on installing 500 MW scale projects to meet their EU renewable obligations by the end of the decade and they have a plan to reach 15 GW of wind power by 2015, almost all of it off-shore. ÒRight now three MW is the standard, there is a lot of experimentation going on in the four to five MW range. The industry will morph into the larger five to seven MW machines by the end of the decade.Ó

Managing reactive power

Another challenge facing the industry, according to Lyons, is integrating large wind projects with the grid. In the early days, wind turbines were designed to trip off when the grid became unstable. Once the grid stabilised, they would resynchronise and come back on line. With large wind projects comprising a significant part of the generation capacity of a given area, tripping off the grid is not the best solution.

ÒThe whole thrust now is to make the wind farms act more like thermal units from a power point level,Ó says Lyons. ÒThere is a tendency of moving from a partial power conversion solution like we use today to a full power conversion solution that separates the dynamics of the rotating machine from the dynamics of grid response. This is now strictly governed by the power electronic converter.Ó

Changing the view from Washington

Rebecca Watson, assistant secretary of the US Department of Interior, told the media in Denver that the wind industry needs to tell a new story. Like changing the paradigm of designing larger turbines, the wind industry also must change the paradigm of how it is viewed Ð perhaps by conveying the idea that wind is not only a $2 billion business for GE in 2005, but also a source of clean energy and local jobs. ÒMaybe there is the wrong impression back in Washington of what wind energy is ... the flower child syndrome. The industry has changed, and that story needs to be told to WashingtonÕs policy makers.Ó

The five states with the greatest wind potential are North Dakota, Texas, Kansas, South Dakota and Montana. In Nebraska, despite its sixth place ranking, development lags behind because of the availability of inexpensive power from municipal utilities throughout the state.

Assessing the energy bill

The Energy Policy Act of 2005, signed in August, added a two-year extension to the wind energy production tax credit, suggesting to industry analysts that strong growth momentum will continue in 2006 and 2007. AWEA believes that this will keep the USA on track to derive 6% of its power from wind by 2020.

Another bright spot in the Act is the requirement that utility system reliability rules to be developed be Ònon-discriminatoryÓ and provide incentives to encourage the construction of new and upgraded transmission lines. AWEAÕs Randall Swisher said these long-term provisions could help Ôlevel the playing fieldÕ and brighten the long-term planning horizon for wind power.

There is concern that the North American Electric Reliability CouncilÕs comments to FERC in FERCÕs currently ongoing generator interconnection proceeding create a higher hurdle for wind than other resources. The Transmission Infrastructure Modernisation is a provision of the bill that adds significant pressure to relieve interstate transmission bottlenecks, and could allow for the designation of corridors between wind-rich areas and the high voltage transmission system, based on the criteria of energy independence and diverse supplies. According to AWEA, the provision does not help with cost allocation, which is typically the more difficult challenge in building the transmission necessary to carry wind power to market from windy areas in the heartland.



US Wind Industry ends most productive year, sustained growth expected for at least next two years

Industry Expected to Build on Momentum;
No Slow-Down for 2006

The U.S. wind energy industry easily broke earlier annual installed capacity records in 2005, installing nearly 2,500 megawatts (MW) or over $3 billion worth of new generating equipment in 22 states, according to the Washington, D.C.-based American Wind Energy Association (AWEA). Instead of the slow year that has previously followed boom years for the industry, 2006 is expected to be even bigger, with installations topping 3,000 MW.

The final tally of 2,431 MW boosted the cumulative U.S. installed wind power fleet by over 35%, bringing the industry's total generating capacity to 9,149 MW1. The previous record capacity figure was set in 2001 when 1,697 MW of new capacity was installed. There are now commercial wind turbine installations in 30 states. The figure was just shy of an expected 2,500 MW because several projects were subject to weather-related delays.

Wind energy facilities now installed in the U.S., AWEA said, will produce as much electricity annually as 2.3 million average American households use2, and will displace emissions of more than 15 million tons of carbon dioxide (the leading greenhouse gas) annually.

"Thanks to Congress’s extending the wind energy production credit before it expired for the first time in the credit’s history, the wind industry is looking forward to several record-breaking years in a row,” said AWEA Executive Director Randall Swisher. “Companies can now plan for growth, create jobs, and provide more clean power to customers nationwide. We are finally beginning to tap into wind energy's enormous potential."

The growth in wind power construction comes at a time when customers across the country are facing electricity and natural gas rate hikes due to the natural gas supply shortage, with 2005-2006 winter gas prices peaking as high as $15/thousand cubic foot (mcf). Monthly average prices range from $6-13/mcf, compared to last year’s monthly average prices of $5-7/mcf. Wind power, which generates energy without using fuel, provides a hedge against rising energy costs because wind energy production is immune from fuel price spikes. AWEA estimates that an installed capacity of 9,149 MW of wind power will save over half a billion cubic feet of natural gas per day (Bcf/day) in 20063, alleviating a portion of the supply pressure that is now facing the natural gas industry and is driving prices upward. The U.S. currently burns about 13 Bcf/day for electricity generation, which means during 2006, wind power will be reducing natural gas use for power generation by approximately 5%.

Other highlights include:

  • California is still the state with the most wind power installed, with 2,150 MW, but Texas is gaining fast with 1,995 MW installed and more proposed for 2006. Iowa remains in third place with 836 MW installed. Minnesota is in fourth with 744 MW, and Oklahoma moves into fifth place with 475 MW.
  • GE Energy turbines accounted for nearly 60% of the new capacity in 2005. Vestas turbines accounted for nearly 30%. Mitsubishi was the third largest wind turbine supplier to the U.S. market, supplying about 8% of the new capacity. Suzlon and Gamesa round out the top five.
  • FPL Energy was the project developer responsible for adding the most new wind power capacity, with over 500 MW of new capacity added to its fleet. PPM Energy was in second place, adding 394 MW4. Horizon Wind Energy added 220 MW5; Invenergy added 200 MW; and enXco added 150 MW.
  • The wind farms completed in 2005, AWEA said, will generate approximately $5 million in payments to landowners annually6 and create skilled, long-term jobs in areas where such employment is scarce, as well as short-term construction jobs and associated economic activity.

A state-by-state listing of existing and proposed wind energy projects is available on AWEA's Web site at http://www.awea.org/projects/index.html The full list of projects installed in 2005 is available on the AWEA newsroom site at http://www.awea.org/newsroom/2005_projects.pdf

 


AWEA, formed in 1974, is the national trade association of the U.S. wind energy industry. The association’s membership includes turbine manufacturers, wind project developers, utilities, academicians, and interested individuals. More information on wind energy is available at the AWEA web site: www.awea.org
Project information is available at www.awea.org/projects

1. 7.45 MW of capacity was reported decommissioned in 2005. Capacity installed as of the end of 2004 was adjusted to 6,725 MW from 6,740 MW due to more information about decommissionings and duplicates.

2. Assuming an average capacity factor of 31% for the total cumulative installed capacity and using the Department of Energy’s Energy Information Agency’s latest household electricity consumption number of 10,656 kWh per year (2001).

3. Assuming that approximately 10 cubic feet of natural gas are required to generate 1 kWh of electricity and that, on average, 80% of wind generation ultimately replaces natural gas-fired electricity.

4. Including a half interest in the Maple Ridge Wind Project, of which 137 MW were reported as installed by year’s end.

5. Including a half interest in the Maple Ridge Wind Project, see previous footnote.

6. Approximately 1,650 wind turbines were installed in 2005. Although leasing arrangements vary widely, a reasonable estimate for income to a landowner from a single utility-scale turbine is about $3,000 a year.